Lake Ontario Outflow Changes
The regulation plan (Plan 2014) specifies a weekly average Lake Ontario outflow from Saturday through the following Friday. Throughout the year, the Lake Ontario outflow, which is managed at the Moses-Saunders Dam, may be modified more frequently depending on the conditions in Lake Ontario and the St. Lawrence River. There are two different types of outflow modifications:
- Operational Adjustments, which do not have to be offset at a later date, and
- Deviations, which are classified as "minor" or "major" and generally do have to be offset at a later date.
Further details are available in the Directive on Operational Adjustments, Deviations and Extreme Conditions (https://ijc.org/en/loslrb/who/directives/deviations)
Access Flow Change Records:
A tabular summary of flow changes is available in an expandable section at the bottom of this page.
Similarly, records of flow changes from previous years are available in an expandable section at the bottom of this page.
Stay Informed:
Would you like to receive outflow notices directly in your inbox? Sign up for RSS-to-email notifications here.
If you have suggestions or questions, please contact us!
Notices
The outflow target for the week of March 15 through March 21 is the applicable Rule Curve flow of 6,660 m3/s.
The outflow target for the week of March 8 through March 14 is the applicable Rule Curve flow of 6,560 m3/s.
As previously noted on February 20, the Lake Ontario outflow was temporarily reduced to 6,230 m3/s on February 17 and to 6,000 m3/s on February 18, in accordance with the Plan 2014 I Limit. As conditions improved, the outflow was gradually increased to 6,100 m3/s on February 20, to 6,300 m3/s February 21, and returned to the applicable Rule Curve flow of 6,540 m3/s on February 22.
The outflow target for the week of March 1 through March 7 is the applicable Rule Curve flow of 6,420 m³/s.
On February 17, following a significant snowstorm and strong winds, the Lake Ontario outflow was reduced to 6,230 m³/s, in accordance with the Plan 2014 I Limit, to promote the stability of the ice covers in the Beauharnois Canal and Lake St. Lawrence. However, the ice conditions did not stabilize and the outflow was further reduced to 6,000 m³/s on February 18. As conditions improved, the Lake Ontario outflow was increased to 6,100 m³/s on February 20. It is expected that the outflow will continue to be gradually increased in the coming days. The outflow target for the week of February 22 through February 28 is the applicable Rule Curve flow of 6,540 m³/s.
The outflow target for the week of February 15 through February 21 is the applicable Rule Curve flow of 6,520 m3/s.
In the remaining weeks of winter, the outflow may be operationally adjusted in accordance with the Plan 2014 I Limit, as needed, to promote the formation and stability of ice covers in the Beauharnois Canal and on Lake St. Lawrence.
The outflow target for the week of February 8 through February 14 is the applicable Rule Curve flow of 6,560 m3/s.
On February 1, during a period of colder temperatures, the Lake Ontario outflow was reduced to 6,230 m3/s, in accordance with the Plan 2014 I Limit, to promote the formation and stability of the ice cover on Lake St. Lawrence. On February 3, as ice conditions improved, the Lake Ontario outflow was increased to the Rule Curve flow of 6,610 m3/s.
If colder temperatures return, the Lake Ontario outflow may be operationally adjusted again in accordance with the Plan 2014 I Limit, as needed, to promote the formation and stability of the ice covers in the Beauharnois Canal and on Lake St. Lawrence.
The outflow target for the week of February 1 through February 7 is the applicable Rule Curve flow of 6,610 m3/s.
On January 27, during a period of colder temperatures and very strong winds, the Lake Ontario outflow was reduced to 6,230 m3/s, in accordance with the Plan 2014 I Limit, to promote the formation and stability of the ice covers in the Beauharnois Canal and on Lake St. Lawrence. On January 28, as ice conditions improved, the Lake Ontario outflow was increased to the Rule Curve flow of 6,720 m3/s.
If colder temperatures return, the Lake Ontario outflow may be operationally adjusted again in accordance with the Plan 2014 I Limit, as needed, to promote the formation and stability of the ice covers in the Beauharnois Canal and on Lake St. Lawrence.
The outflow target for the week of January 25 through January 31 is the applicable Rule Curve flow of 6,720 m3/s.
Ice-building temperatures returned on January 19 and the Lake Ontario outflow was reduced to 6,230 m3/s in accordance with the Plan 2014 I Limit. An additional 2 km of ice, for a total of 16 km, has accumulated in the Beauharnois Canal and a partial ice cover has formed immediately upstream of the Moses-Saunders Dam. The Lake Ontario outflow was increased to 6,530 m3/s on January 22 and to 6,720 m3/s on January 23.
If colder temperatures return, the Lake Ontario outflow may be operationally adjusted again in accordance with the Plan 2014 I Limit, as needed, to promote the formation and stability of ice covers in the Beauharnois Canal and on Lake St. Lawrence.
The outflow target for the week of January 18 through January 24 is the applicable Rule Curve flow of 6,760 m3/s. However, the Lake Ontario outflow will continue to be operationally adjusted in accordance with the Plan 2014 I Limit, as needed, to promote the formation and stability of ice covers in the Beauharnois Canal and on Lake St. Lawrence.
On January 7, slushy ice slowly began to accumulate in the Beauharnois Canal. On January 9, strong winds caused the ice to move, and the Lake Ontario outflow (at Moses-Saunders Dam) was reduced to 6,260 m3/s with the goal of stabilizing the ice cover. However, the ice cover did not stabilize and the Lake Ontario outflow was then further reduced to 5,700 m3/s. As ice conditions improved, the Lake Ontario outflow was gradually increased on January 11, 12, and 13, and was set to the Rule Curve flow of 6,800 m3/s at noon on January 15.
Approximately 14 km of ice has accumulated in the Beauharnois Canal. A significant ice cover has not yet formed on Lake St. Lawrence upstream of the Moses-Saunders Dam. It is expected that the outflow will need to be decreased again next week when colder temperatures return.
The outflow target for the week of January 11 through January 17 is the applicable Rule Curve flow of 6,800 m3/s. However, the Lake Ontario outflow has been reduced to 6,260 m3/s to promote the formation of an ice cover in the Beauharnois Canal.
During the winter months, the outflow will continue to be operationally adjusted in accordance with the Plan 2014 I Limit, as needed, to promote the formation and stability of ice covers in the Beauharnois Canal and on Lake St. Lawrence.
For more information,
- FAQ 2.7 “What actions does the Board take to manage ice conditions in the St. Lawrence River during the winter?”: https://ijc.org/en/loslrb/watershed/faq/2#2-7
- FAQ 4.8.4 “What is the I Limit?”: https://ijc.org/en/loslrb/watershed/faq/4#4-8-4
- This video demonstrates the importance of ice management in the St. Lawrence River: https://vimeo.com/168823489
- This video discusses winter operations under Plan 2014: https://vimeo.com/670845537
The outflow target for the week of January 4 through January 10 is the applicable Rule Curve flow of 6,820 m3/s.
The outflow target for the week of December 28, 2024 through January 3, 2025 is the applicable Rule Curve flow of 6,780 m3/s.
Tabular Summary of Lake Ontario Outflow Changes
DATE | HOUR | OUTFLOW | OUTFLOW | NOTES |
(YYYY-MM-DD) | (HHMM) | (m3/s) | (cfs) | |
2025-03-15 | 0001 | 6,660 | 235,200 | Rule Curve |
2025-03-08 | 0001 | 6,560 | 231,700 | Rule Curve |
2025-03-01 | 0001 | 6,420 | 226,700 | Rule Curve |
2025-02-22 | 1201 | 6,540 | 231,000 | Rule Curve |
2025-02-21 | 1101 | 6,300 | 222,500 | Operational Adjustment for I Limit |
2025-02-20 | 1501 | 6,100 | 215,400 | Operational Adjustment for I Limit |
2025-02-18 | 1101 | 6,000 | 211,900 | Operational Adjustment for I Limit |
2025-02-17 | 1701 | 6,230 | 220,000 | Operational Adjustment for I Limit |
2025-02-15 | 0001 | 6,520 | 230,300 | Rule Curve |
2025-02-08 | 0001 | 6,560 | 231,700 | Rule Curve |
2025-02-03 | 1201 | 6,610 | 233,400 | Rule Curve |
2025-02-01 | 0001 | 6,230 | 220,000 | Operational Adjustment for I Limit |
2025-01-28 | 1401 | 6,720 | 237,300 | Rule Curve |
2025-01-27 | 1501 | 6,230 | 220,000 | Operational Adjustment for I Limit |
2025-01-23 | 1501 | 6,720 | 237,300 | Operational Adjustment for I Limit |
2025-01-22 | 1501 | 6,530 | 230,600 | Operational Adjustment for I Limit |
2025-01-19 | 1601 | 6,230 | 220,000 | Operational Adjustment for I Limit |
2025-01-18 | 0001 | 6,760 | 238,700 | Rule Curve |
2025-01-15 | 1201 | 6,800 | 240,100 | Rule Curve |
2025-01-13 | 1201 | 6,460 | 228,100 | Operational Adjustment for I Limit |
2025-01-12 | 1201 | 6,260 | 221,100 | Operational Adjustment for I Limit |
2025-01-11 | 1201 | 6,000 | 211,900 | Operational Adjustment for I Limit |
2025-01-09 | 1801 | 5,700 | 201,300 | Operational Adjustment for I Limit |
2025-01-09 | 1301 | 6,260 | 221,100 | Operational Adjustment for I Limit |
2025-01-04 | 0001 | 6,820 | 240,800 | Rule Curve |
2024-12-28 | 0001 | 6,780 | 239,400 | Rule Curve |
Outflow change records from previous years
To view outflow change records from previous years, please use the links below: