Ordonnances d'approbation

(Disponible en anglais seulement)

9 November, 1915

For approval of a dam and power canal and the obstruction, diversion and use of the waters of the St. Croix River at Grand Falls in the State of Maine and the Province of New Brunswick: Maximum elevation 202.0 feet m.s.l.
 

6 October 1931

For the obstructions of the waters of the St. Croix River at Grand Falls in the State of Maine and the Province of New Brunswick. Increase in elevation to 203.5 feet m.s.l.

 

3 October 1923

Erection and repairs of fishways in the St. Croix River at St. Croix Gas and Light and Canadian Cottons Mill Dam. ( Note: the St. Croix Gas and Light Dam was destroyed by fire in 1924.  The Canadian Cotton Mills Dam was reconstructed in 1934 and is known as Milltown Dam.)


2 October, 1934

For the reconstruction of a dam across the St. Croix River from Milltown in the Province of New Brunswick to Milltown in the State of Maine.
 

15 October, 1965

For the construction of a storage dam in the St. Croix River at Vanceboro, Maine and St. Croix, New Brunswick:
 

Discharge from Spednic Lake
 
200 cfs ( 5.66 m3\s ) minimum
Elevation of Spednic Lake
 
385.86 feet (117.611 metres ) maximum
Between 1 October and 30 April
 
371.50 feet (113.233 metres) minimum
Between 1 May and 30 September
 
376.50 feet ( 114.759 metres ) minimum
Discharge from East Grand Lake
 
75 cfs ( 2.12 m3\s ) minimum
Elevation of East Grand Lake 434.94 feet (132.571 metres ) maximum
427.94 feet ( 130.438 metres ) minimum

 

16 November, 1982

For the reconstruction of the diversion dike in the St. Croix River near Baileyville, Maine.

 

Printer friendly version